After the 9-1 defeat of this proposal at the Village Planning Commission in October, Vestar went on to do nothing until the November meeting.
Then asked for another 60 days and did nothing, then they got an "Indefinite" extension after January 4th.
ROUND 2 ...
Revised plans have been submitted in August 2024.
It appears their new plan is to reduce the grocery store size and take out Drive throughs, but indicate that through a separate process these restaurants might still be included. A bait and switch approach.
Because once the rezoning is approved, there will be little standing in their way to submit "change requests" to subsequently include these.
ENOUGH IS ENOUGH !
It will be unfair and unacceptable to start this process over after it has been denied. The blatant stalling tactics are showing complete disrespect and is wasting everybody's time. The families of this neighborhood should not be asked to keep coming to meetings where nothing is being decided.
We're fighting for our community character, but how long should we expected to continue to do this. We need to move on.
NEW RESIDENTIAL BUILDER HAS APPLIED
We have learned that a residential builder has applied for the remainder of the superblock 12 parcel and probably would be interested in the acres in question. This should be a huge factor of consideration in this rezoning case as it was always part of the plan for this to be residential.
OTHER CONSTRUCTION
Since last year, you will have noticed that many other projects have been started. Some are residential, others are commercial. These were done PER THE DESERT RIDGE MASTER COMMUNITY PLAN!
WHAT WE ASK
Please attend your local HOA meetings where Vestar will present the revised plans. Ask questions and share your concerns.
Ask them why they won't consider building on pre-zoned commercial land. Why next to a high school and elementary school?
Why attract more traffic and new issues into our community?
Your attendance is crucial to this case.
Please click on this button below to see the upcoming meetings and how to attend and also how to email your concerns to this committee ahead of time.

> This request is still NOT APPROVED.
> Next meeting is October 1, 2024 at 6:30pm at Paradise
> Request is now back with the Desert View Village Planning committee
> Next step after that is City Planning committee in November.
Below is a summary of events and additional information we've gathered regarding this case.
On October 3rd the Desert View Village Planning Commission voted overwhelmingly to dismiss this request by a vote of 9-1. In reference of case GPA-DSTV-2-23-2 and Case GPA-DSTV-3-23-2 and Case Z-39-23-2
City Planning Commission meeting took place on november 2nd. At this meeting, Vestar requested a continuance (delay) of the case hearing.
Normally this would be a 30 day period, but they actually requested 60 days because of dealing with the Arizona State Land Department and their review process.
Their request was granted with the stipulation that Vestar would share with the opposing residents their changed plan and leave enough time for them to review.
The core opposition group got invited to review the revisions Vestar was going to make.
This meeting revealed NOTHING was done to revise the plan, nor had Vestar spoken to the State Land Department.
They only verbally provided new ideas that they weren't willing to commit to paper.
Vestar asked for further delays and received "indefinite" extension from the city planning committee to revise their plans and get the community onboard.
Updated plans have been published for Black Mountain Blvd project.
They reduced the size of the grocery, but included a stipulation that Drive throughs may not be included in this version of the plan, but could be added through a separate process. #baitandswitch
Please check your Fireside and Sky Crossing community pages for upcoming meetings.
Revised Plans
( CLICK HERE )
Dear Planning committee members, Mayor, Councilman,
When is enough, enough? That will be the question on the upcoming January 4th review meeting for a possible continuance request for this case.
Me and the 842 petition signers find this unfair and unacceptable request and so should you.
A quick summary of events timeline that will show that Vestar has now had 10 weeks to take actions and has done nothing significant;
To put insult to injury, Vestar also announced during December 11th meeting that they would request for another continuance on January 4th.
This is where we draw the line. Vestar has had 10 full weeks to work on their proposal and did nothing!!
Whilst Vestar is claiming to care for Desert Ridge and boasts about their involvement, the blatant stalling tactics deployed in this case should not be tolerated and residents should not be asked to have this request hovering over our community for any longer.
Based on this, I ask the committee to consider to deny this potential request as it’s baseless, holidays were already factored in last time and now it will start causing undue hardship for our community.
We’re fighting for our community character and Residents cannot be asked to fight Vestar, their disingenuous actions and their attorneys for much longer. It’s not a level playing field.
Families that already have busy lives and volunteers like yourselves shouldn’t be treated like this by Vestar and their attorneys.
The January 4th meeting is in the middle of our school vacation! We shouldn’t be asked to come to meetings where nothing new is being discussed, nor should this committee.
Our residents are prepared and ready to present our opposition case.
We compel this committee to move forward with the review and voting process on January 4th, and hopefully you will agree with us and the VPC that it should be dismissed immediately and without compromise.
Any consideration to grant a continuance request should have very specific objectives and deliverables that Vestar will be held accountable for.